Matt Dursh Profile Banner
Matt Dursh Profile
Matt Dursh

@MattDursh

Followers
8,149
Following
925
Media
780
Statuses
4,878

Professional Engineer • Bridge Design • Civil Engineering • Design Build • Accelerated Bridge Construction • e/acc

Tampa, FL
Joined September 2015
Don't wanna be here? Send us removal request.
Explore trending content on Musk Viewer
Pinned Tweet
@MattDursh
Matt Dursh
7 months
Bridge design for vessel collision. A🧵 The main span of the Francois Scott Key Bridge is 1300 ft. It also has 185 ft of clearance, making this a massive bridge. This type of bridge is considered complex. Baltimore is in for a long haul before replacement. Here is why. 1/x
Tweet media one
638
4K
24K
@MattDursh
Matt Dursh
7 months
There are many things left to talk about here, but on a plane now. I specialize in bridge design of long bridges over navigable waters. Thanks for reading and happy to answer all questions. 12/12
224
203
9K
@MattDursh
Matt Dursh
9 months
wait till the end
142
914
5K
@MattDursh
Matt Dursh
7 months
Modern bridges deal with vessel collision two ways. The first is to use a dolphin. This is a mass of rock, sand, and steel that serves to stop the vessel before it makes contact with the bridge. Likely the new bridge replacement will use a dolphin as one method. 6/x
Tweet media one
46
226
4K
@MattDursh
Matt Dursh
7 months
This bridge was going to fail from this event. It simply was not designed for an equivalent static force that is well over 3 million pounds. The container ship, assuming the navigation channel is centered, veered over 500 feet off course. Why did the whole thing fall? 4/x
17
179
4K
@MattDursh
Matt Dursh
7 months
The Baltimore bridge collapsed because it got hit by container ship. What failed first? It appears the bow of the ship made contact with the vertical columns that supported the truss superstructure, causing it to have a cascade failure. 3/x
21
227
4K
@MattDursh
Matt Dursh
7 months
We design modern bridges for ship impact, but this was not always the case. In 1980 the Sunshine Skyway Bridge also collapsed from vessel strike. The photo below is the original Skyway. Similar bridges and identical failure. The Skyway collapse changed bridge design. 2/x
Tweet media one
25
231
4K
@MattDursh
Matt Dursh
7 months
The whole truss fell because this is a continuous bridge. This means that the 3 span unit behaves as as one. If one span fails, the maximum dead loads redistributes. This provides benefits to load resistance and is how we design modern bridges for this. How? 5/x
Tweet media one
18
169
4K
@MattDursh
Matt Dursh
7 months
Baltimore is going to be without a critical bridge for a long time. Tampa's Skyway bridge took 7 years, but this will be done sooner, hopefully much sooner. What needs to be done? Well, a lot. Can the approach spans be salvaged? 9/x
20
136
3K
@MattDursh
Matt Dursh
7 months
The second is to design the bridge to take the vessel strike and resist the event. This is a massive undertaking with a central focus: don't collapse. We will see localized failures, but maintain global stability. This load could be well over 3 million pounds. 7/x
10
118
3K
@MattDursh
Matt Dursh
7 months
To resist that much load to stop a vessel, we need a flexible bridge and a lot of foundations, such as piling or drilled shafts. Typically this is more foundation needed than to simply resist earthquakes, hurricanes, and every day loads. So where do we go from here? 8/x
11
104
3K
@MattDursh
Matt Dursh
7 months
The approach spans are likely fine. But are they tall enough to support the new main span? Does the bridge need more vertical clearance? Officials will nees to ask... do they fully replace the bridge in full, or attempt to reopen sooner with only the main span? 10/x
14
92
3K
@MattDursh
Matt Dursh
7 months
The main span is not easy to design or build, unless they make a decision to go to a smaller span bridge (less than 375ft). But that comes with new challenges particularly with how close the piers will be to the navigation channel. 11/x
14
85
3K
@MattDursh
Matt Dursh
8 months
@scottew proof that dark mode is the baseline
9
21
2K
@MattDursh
Matt Dursh
4 months
The navigation channel has fully reopened after the collapse of the Francis Scott Key Bridge. A total of six bridge spans fell after the M/V Dali struck the bridge. It took 76 days to remove over 50,000 tons of the wreckage. A 🧵 on next steps to rebuild the Key Bridge. (1/8)
Tweet media one
22
204
2K
@MattDursh
Matt Dursh
7 months
@xtbot Tunnels have their own sets of challenges. A bridge can be rebuilt here designed to prevent a tragedy like this again.
14
14
1K
@MattDursh
Matt Dursh
6 months
Recent footage on the progress at the Francis Scott Key Bridge. As explained by a Professional Engineer and Bridge Designer. My first video! What do you think?
138
186
1K
@MattDursh
Matt Dursh
1 month
The Design Builder has been selected for the rebuild of the Francis Scott Key Bridge! The design of the replacement bridge begins now. This is what happens next. A 🧵 about bridge design and construction. (1/12)
Tweet media one
41
159
874
@MattDursh
Matt Dursh
7 months
@quartercast1 Bad stat in hindsight. Skyway was a 4+ mile bridge fully rebuilt.
9
2
864
@MattDursh
Matt Dursh
6 months
The collapsed steel spans should not be reused. When verifying safety for traffic, many members will be compromised due to permanent deformations and other signs of distress. The continuous bridge was built using temporary towers, this changes the "locked-in" stress. 1/x
Tweet media one
@elonmusk
Elon Musk
6 months
@shivon If you reuse the truss steel that fell, it could be functioning in 3 to 6 months. The repair should be put to commercial bid with a massive incentive for early and safe completion.
700
260
3K
86
115
850
@MattDursh
Matt Dursh
5 months
One of the first vessels to transit the Limited Access Channel at the Francis Scott Key Bridge. Gives a sense of scale of just how large the Dali is.
30
193
830
@MattDursh
Matt Dursh
6 months
Bridge Analysis to remove the Francis Scott Key Bridge. A 🧵 Extracting the steel at the bottom of the Patapsco River will be complex. The structural steel arch still has capacity to it, similar to bending a paperclip. How do you determine the sequence to cut? (1/x)
Tweet media one
42
88
669
@MattDursh
Matt Dursh
4 months
How will the Francis Scott Key Bridge be rebuilt? The Transportation Authority says it will be a Progressive Design Build. The winning contractor will be chosen by qualifications and the construction cost provided later. A brief 🧵 about contracts for roads and bridges. 1/10
Tweet media one
37
96
639
@MattDursh
Matt Dursh
4 months
The deep draft navigation channel at the Francis Scott Key Bridge recovery has been fully restored. The Fort McHenry channel is 50 feet deep to the mudline and and is 700 feet in width. The vertical clearance is 214 feet due to the nearby overhead electrical lines.
11
72
596
@MattDursh
Matt Dursh
10 days
The Kinser Bridge has collapsed near Greenville, Tennessee from severe flood waters of the Nolichuky River. This was caused by scour on the foundations of the bridge, removing the supporting mudline soil from the piers.
21
264
564
@MattDursh
Matt Dursh
7 months
@autumnpard My career is designing and building bridges like this. This is a tragedy.
15
2
506
@MattDursh
Matt Dursh
6 months
This hydraulic grabber is about to put in some serious work at the Francis Scott Key Bridge recovery. It's self weight is 400,000 pounds and it can extract over 2,000,000 pounds. The capacity will be limited by the crane that wields it. I cannot wait to see it in action.
Tweet media one
24
62
494
@MattDursh
Matt Dursh
10 days
The approaches to the Lake Lure Flowering Bridge in Chimney Rock, North Carolina has scoured away. This historic three span arch bridge was built in 1925 and carried traffic until a new bridge opened in 2011. The bridge supported an expansive garden before Hurricane Helene.
16
154
505
@MattDursh
Matt Dursh
6 months
A huge 440 ton section of the Francis Scott Key Bridge being transported. It was partially submerged prior to lifting. Steel truss section is so large it is being floated to disposal instead than placed on a barge. The scale of this operation is incredible.
19
103
469
@MattDursh
Matt Dursh
5 months
It has been just over 30 days since the collapse of the Francis Scott Key Bridge. This video reviews the progress made in the recovery and the scale of the mobilization.
21
95
461
@MattDursh
Matt Dursh
5 months
The Dali has been refloated and is no longer at the Francis Scott Key Bridge site! Five tugboats are transiting the vessel to a local marina. There the remainder of the steel and concrete on the bow will be removed and all containers offloaded.
Tweet media one
16
83
437
@MattDursh
Matt Dursh
5 months
The refloat of the MV Dali away from the Francis Scott Key Bridge. Now moored at the Seagirt Marine Terminal. The 50 foot full depth navigable channel has been partially restored with a 400 feet horizontal clearance All commercial vessels can now enter and exit the port.
12
73
392
@MattDursh
Matt Dursh
5 months
Before and after photos of the Francis Scott Key Bridge concrete column sitting on the Dali. A full depth saw cut was made through the concrete column for removal. The inner hollow core of the column can be seen. Incredible work being done at the recovery effort.
Tweet media one
Tweet media two
Tweet media three
21
54
350
@MattDursh
Matt Dursh
15 days
The Francis Scott Key Bridge collapsed after vessel collision from the MV DALI. This tragedy was entirely avoidable. A small change in course would have prevented ship impact. All means to control the the motor vessel were unavailable. A 🧵 about the unseaworthy Dali. 1/9
Tweet media one
28
81
354
@MattDursh
Matt Dursh
1 month
Time is of the essence to rebuild the Francis Scott Key Bridge. I will provide updates as milestones are reached. I am a Professional Engineer, bridge designer, and design build project manager for heavy civil infrastructure projects. Thank you for reading my 🧵. (12/12)
Tweet media one
23
12
350
@MattDursh
Matt Dursh
6 months
A temporary channel has opened at the Key Bridge. The first vessel to use the temporary channel is the tugboat Crystal Coast. It is pushing a fuel barge carrying jet fuel that supplies the Department of Defense.
14
52
340
@MattDursh
Matt Dursh
23 days
Bridge collapse in Dresden, Germany. The Carola Bridge fell into the waters of the Elbe River on September 11. A 🧵about bridge design. (1/9)
Tweet media one
20
50
347
@MattDursh
Matt Dursh
5 months
Great angle of the controlled demolition of the Francis Scott Key Bridge.
18
68
338
@MattDursh
Matt Dursh
5 months
First views from atop the Dali at the Francis Scott Key Bridge recovery. Also confirmed is the use of precision cutting for a controlled demolition of the truss. Critical connections have been marked on the structural steel. There are pre cuts made into the webs of the beams.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
20
78
329
@MattDursh
Matt Dursh
9 months
@10x_er she made her tik tok, then watched her tik tok. just like the predictable clicking of a clock.
0
2
322
@MattDursh
Matt Dursh
6 months
The 35' depth limited access channel at the Francis Scott Key Bridge recovery will open ahead of schedule. Vessels will transit on the left side of this photo starting April 25. This is wonderful news and demonstrates the quality work being done.
Tweet media one
13
49
318
@MattDursh
Matt Dursh
6 months
New sonar images of the Francis Scott Key Bridge shows incredible perspective and details. 🧵 This is the main span channel pier opposite of the Dali impact. You can see the detail of the column, footing, and truss. (1/3)
Tweet media one
9
42
309
@MattDursh
Matt Dursh
6 months
Largest crane pick seen so far for the Key Bridge. Full depth section of the truss. Top and bottom chords. This is with the Chesapeake 1000 ton crane. First pick since mobilizing on site?
Tweet media one
12
51
307
@MattDursh
Matt Dursh
22 days
The worst flooding in over 150 years in Vienna, Austria as the Danube River continues to rise. Bridge piers resist forces from the water, remaining stable as the soil that supports the foundations scours away. Maximum stress scenario in bridge design.
19
47
311
@MattDursh
Matt Dursh
4 months
The wreckage of the Francis Scott Key Bridge has almost been fully removed. One section of the truss remains before the full width reopening of the channel. That section was partially resting on the Dali. Latest schedule update indicates full restoration by June 10th.
Tweet media one
20
51
293
@MattDursh
Matt Dursh
10 months
Technology Optimism Effective Acclerationism American Exceptionalism
Tweet media one
24
33
279
@MattDursh
Matt Dursh
5 months
The steel truss of the Francis Scott Key Bridge is being removed from the bow of the Dali. The reinforced concrete deck and floor beams that supported it can now be seen. The extent of damage on the Dali is starting to show.
16
67
283
@MattDursh
Matt Dursh
5 months
Precision cutting charges have been placed on the Francis Scott Key Bridge. Detonating the charges and sending the steel truss into the water is set for Saturday afternoon. Surprisingly, the crew on the Dali is to remain aboard and shelter in place during the event.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
24
51
276
@MattDursh
Matt Dursh
5 months
A bridge has partially collapsed after a barge collision with a pier. The Pelican Island Causeway is the only route on and off the island in Galveston, Texas. Railroad spans collapsed, causing damage to the vehicular bridge. A 🧵 about this bridge and next steps. (1/10)
Tweet media one
18
35
271
@MattDursh
Matt Dursh
4 months
The final steel truss section of the Francis Scott Key Bridge has been pulled from the Patapsco River. It was well embedded in the mudline, taking "extensive operations" to extract it. The Chesapeake 1000 crane carried this piece to Sparrows Point for disposal. Great work.
Tweet media one
4
43
264
@MattDursh
Matt Dursh
6 months
This is an 880,000 pound crane pick at the Francis Scott Key Bridge. Less than 1 min explainer video by a Professional Engineer and Bridge Designer. Next video is in the works.
30
39
261
@MattDursh
Matt Dursh
5 months
More angles of the controlled demolition of the Francis Scott Key Bridge.
15
59
259
@MattDursh
Matt Dursh
5 months
The hydraulic grabber is putting in some serious work at the Francis Scott Key Bridge recovery. Keep in mind the yellow grabber itself is 29 feet tall. Here it is removing some floor beams and stringers. Those pieces of structural steel supported the concrete deck.
Tweet media one
11
49
247
@MattDursh
Matt Dursh
11 months
"No one is coming to save you, so go out in the world, build good things, useful things, things that people like and use." - @IterIntellectus e/acc and the Techno-optimists are creating. Come build with us.
Tweet media one
@IterIntellectus
vittorio
11 months
Ok guys, gather around. As I feel obliged by the state of matters, I will give you my very dumb take on the current thing: As I see it now, this is war. Ideological, philosophical, memetic. It’s not a war for land, power, or money (even though these are at stake in the short
Tweet media one
66
88
584
10
18
249
@MattDursh
Matt Dursh
6 months
the feedback and response that i have gotten on my video is really incredible. thank you. will keep more videos coming.
@MattDursh
Matt Dursh
6 months
Recent footage on the progress at the Francis Scott Key Bridge. As explained by a Professional Engineer and Bridge Designer. My first video! What do you think?
138
186
1K
22
18
252
@MattDursh
Matt Dursh
4 months
Thank you for reading my 🧵. I am a Professional Engineer, a bridge designer for long bridges over water, and design manager for Design Build projects. I will continue to post about civil infrastructure. Fall 2028 reopening is an aggressive schedule that can be done. (8/8)
Tweet media one
4
9
253
@MattDursh
Matt Dursh
3 months
The vertical clearance for the rebuild of the Francis Scott Key Bridge has not been finalized. Existing bridge had a navigable clearance of 184 feet. Recently built electrical lines now controls at 214 feet. A 🧵 on construction cost of transportation infrastructure. 1/x
Tweet media one
20
41
251
@MattDursh
Matt Dursh
5 months
Here is how the precision cutting demolition will be done on the Francis Scott Key Bridge. The steel truss sitting on the Dali will use explosive charges to cut the steel. The placement locations and timing of the charges will cause it to fall off the bow and into the water.
18
44
239
@MattDursh
Matt Dursh
6 months
The significant risks of reusing the fallen spans far out weighs the potential schedule benefits. It is important to consider this as an option in the bridge recovery, but I strongly advise against it. Rebuild with new American steel. 6/6
Tweet media one
23
10
241
@MattDursh
Matt Dursh
5 months
My bridge under construction in Florida. 30 inch concrete piles are in a temporary steel template. Templates are used to install the pile plumb and in the correct position. These are driven into the ground using a diesel impact hammer, striking the pile 1,000s of times.
Tweet media one
18
16
220
@MattDursh
Matt Dursh
9 days
Devastating Nolichucky River flooding from Hurricane Helene has collapsed two bridge spans on Interstate 26 in Erwin, Tennessee. Soil embankment behind bridge abutments, where a bridge starts from land, was washed away by the flood waters. 🧵 about highway bridge design. 1/6
Tweet media one
16
48
217
@MattDursh
Matt Dursh
6 months
Engineers are installing devices on the Francis Scott Key Bridge to measure forces inside the beams. The loads and stress seen by the truss will change during each step of removal. Depending on the statics, it may increase or decrease. What device can they use? (1/3)
Tweet media one
17
31
209
@MattDursh
Matt Dursh
11 days
Tampa General Hospital is on Davis Island in Tampa Bay, which is an area that very vulnerable to storm surge. The hospital placed a temporary barrier that resists up to 15 feet of storm surge, allowing them to maintain operations. It worked well!
8
30
215
@MattDursh
Matt Dursh
6 months
New tunnel completed in Virginia. One more to go after the tunnel boring machine makes a U turn. Awesome.
10
24
204
@MattDursh
Matt Dursh
26 days
Vessel collision on a cable stayed bridge in the Netherlands. The structural steel of the bridge was struck because the vessel violated the vertical clearance of the waterway. The bridge will be inspected and repairs done to the steel superstructure.
15
38
208
@MattDursh
Matt Dursh
6 months
More sections of the steel truss getting removed. When the biggest crane is putting in work it is a sign of progress being made.
Tweet media one
12
33
199
@MattDursh
Matt Dursh
6 months
First look at underwater survey of the Key Bridge. Good sign is there are still large portions of intact bridge to work with. But where the truss has failed it is fully collapsed on itself. It also is partially under the mudline, increasing the loads on the crane.
Tweet media one
19
28
191
@MattDursh
Matt Dursh
5 months
Short video on a 440 ton section of the Francis Scott Key Bridge. Includes some info about the Chesapeake 1000 crane and naming of the truss itself. Included unit conversions for you metric system enjoyers. This info will be used as reference material for an upcoming video.
7
45
192
@MattDursh
Matt Dursh
7 months
that masculine urge to hire all your friends to go and build something never done before.
9
10
188
@MattDursh
Matt Dursh
6 months
Evaluate what happens after the cut, does the structure move and reposition? Does the structural steel have the capacity to resist the salvage loads and avoid rupture during lifting? We will see the largest crane pick they can make with the 1000 ton crane. (5/5)
16
4
194
@MattDursh
Matt Dursh
2 months
The Francis Scott Key Bridge replacement has received Federal environmental approvals. The process was expedited because the new bridge will be the same number of lanes and built on the existing footprint. This avoids a long procedure of evaluating impacts for the rebuild.
Tweet media one
15
32
188
@MattDursh
Matt Dursh
4 months
Thank you for reading my 🧵. I am a professional engineer, bridge designer, and design manager for design build heavy civil infrastructure projects. If interested in more content like this, make sure to follow and distribute. 10/10
10
10
187
@MattDursh
Matt Dursh
6 months
Work Zone progress at the Francis Scott Key Bridge. 1. Chesapeake 1000 clearing steel from temp channel. 2. Weeks 533 picking containers from Dali. 3. Deck being crushed and dredged. This reduces load and provides access to remove the second half of the truss.
Tweet media one
9
26
170
@MattDursh
Matt Dursh
6 months
The gas and electric utilities in proximity to the Francis Scott Key Bridge Recovery. What can be considered to enhance safety and facilitate schedule? Can the electrical transmission lines be de-energized and temporarily removed to enable crane activities on both sides? 1/8
Tweet media one
15
26
168
@MattDursh
Matt Dursh
6 months
Half section of the Francis Scott Key Bridge truss. Top of the bridge is on the left in photo. Looks to have been extracted from the mudline. Chesapeake 1000 doing great work.
Tweet media one
5
19
168
@MattDursh
Matt Dursh
2 months
Segmental concrete bridges. This type of bridge design uses a specialized launching gantry to install the superstructure. The construction methodology in this video is called span by span construction.
19
20
167
@MattDursh
Matt Dursh
4 months
One of the last pieces of the Francis Scott Key Bridge steel truss has been removed. This was partly resting on the Dali. This section suspended the vehicular concrete deck below it The next step will use the hydraulic grab to extract the floor beams and deck from the mud.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
5
28
165
@MattDursh
Matt Dursh
6 months
A new temporary channel has opened at the Francis Scott Key Bridge. Vessels will need to sail near the electrical towers. The Fort Carrol temporary alternate channel is 300 foot wide with a vertical clearance of 135 feet and a controlling depth of 20 feet. Good progress!
Tweet media one
6
28
162
@MattDursh
Matt Dursh
5 months
How it started vs how it's going at the Francis Scott Key Bridge recovery.
Tweet media one
Tweet media two
5
21
160
@MattDursh
Matt Dursh
28 days
Bridge design for extreme storms. A 🧵 Two spans of the Phong Chau Bridge in Vietnam collapsed during Typhoon Yagi. This bridge failure mechanism is one of the most common. What happened and how is it prevented? (1/10)
Tweet media one
8
25
163
@MattDursh
Matt Dursh
3 months
The fender did it's job in redirecting the vessel away from the bridge piers and back to the channel. This one is made of prestressed concrete piles. Each support is a vertical plumb pile and an angled battered pile that absorb the collision energy.
9
11
161
@MattDursh
Matt Dursh
6 months
How it started vs How it's going. Francis Scott Key Bridge edition.
10
25
153
@MattDursh
Matt Dursh
10 days
Walter's Dam in North Carolina, east of the Smoky Mountains National Park, has not failed! County Mayor initially reported of catastrophic failure. But the power company has flood gate control and the Waterville dam is performing as expected. Evacuation still underway. 🧵1/3
Tweet media one
7
15
154
@MattDursh
Matt Dursh
6 months
The above water photography does not capture the significant challenges underwater. What is not seen is the reinforced concrete deck that is still attached to the steel. A web of rebar and concrete poses significant hazards. It also is heavy. (3/x)
Tweet media one
1
8
151
@MattDursh
Matt Dursh
7 months
terrible to see a bridge collapse. we design modern bridges for vessel collision, but this one was built in the 70s before standards changed. very similar bridge to Sunshine Skyway collapse in the 80s, which is what changed the design codes.
10
23
146
@MattDursh
Matt Dursh
6 months
Engineers will use hand calculations and 3D finite element models to perform static analysis. This will determine how the structure is supporting itself and how it's weight is distributed. Cut points and lift locations will be evaluated for several criteria. (4/x)
Tweet media one
5
4
148
@MattDursh
Matt Dursh
6 months
You start with the existing bridge plans. They will be used to determine the weight of the bridge and the capacity of the steel members. Lift points will be established to confirm the damaged steel can support itself during removal. 3D survey will be used extensively. (2/x)
Tweet media one
3
8
145
@MattDursh
Matt Dursh
6 months
Temporary steel towers were used to support the bridge during construction. Their use and timing of removal dictates when each steel member is fully engaged to support the self weight of the bridge. If one is removed too soon, or not used at all, this changes everything. 2/x
Tweet media one
2
2
140
@MattDursh
Matt Dursh
5 months
Crane on the right is lifting a man basket with two workers inside. The Francis Scott Key Bridge was the second largest bridge of it's type in the world.
Tweet media one
6
13
142
@MattDursh
Matt Dursh
15 days
The collapse of the Francis Scott Key Bridge caused a loss of life for six construction workers maintaining on the Key Bridge. Repairing the riding surface of the bridge deck to improve driving conditions. Performing important maintenance. If only the Dali had done so. 9/9
Tweet media one
12
10
144
@MattDursh
Matt Dursh
3 months
The Dali has exited the Port of Baltimore and is heading to Norfolk, Virginia. The containers have not been offloaded yet. Portions of the reinforced concrete deck has been removed. The collapsed column of the Francis Scott Key Bridge still remains on the bow.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
13
36
135
@MattDursh
Matt Dursh
5 months
The precision cutting of the Francis Scott Key Bridge was a success. Locations where charges were placed on the structural steel truss can be seen. The damage to the Dali is extensive but is planned to refloat next week. Navigation channel will be reopened soon.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
3
31
135
@MattDursh
Matt Dursh
6 months
Removing the collapsed Francis Scott Key Bridge. A🧵 These are some of the challenges and solutions that should be considered. Time is of the essence and safety is paramount. Accelerate Bridge Construction (1/X)
Tweet media one
14
18
131
@MattDursh
Matt Dursh
4 months
Concrete pile driving using a diesel impact hammer. Thousands of hammer blows are used to advance the pile and achieve capacity. Gauges attached to the pile measure acceleration and strain during each strike. We use that info to determine the bearing capacity of the pile.
19
9
131
@MattDursh
Matt Dursh
6 months
Unless the bridge was rebuilt in the same order with the same tower locations, there will be changes to the self weight stress in the steel. Would that change result in overloading of any member or connection? Only rigorous engineering can answer this with confidence. 3/x
Tweet media one
3
2
128
@MattDursh
Matt Dursh
10 months
e/acc is about to reach escape velocity. extreme optimism is proliferating. morale maxxing will continue.
@JaelRuble
Jael Ruble
10 months
@lexfridman is interviewing @BasedBeffJezos today 🔥 Happy white pill Wednesday ♥️
11
6
108
5
9
129
@MattDursh
Matt Dursh
9 months
@oneleftshoe this is a really good suggestion
3
0
130
@MattDursh
Matt Dursh
11 months
New machining. New tooling. New frontiers. e/acc means and methods are for builders
@entelechiada
Entelechiada
11 months
“sovereign AI infrastructure” — multibillion dollar growth opportunity in coming years
3
3
26
11
9
129
@MattDursh
Matt Dursh
23 days
Thanks for reading my 🧵. I am a Professional Engineer and Bridge Designer. I post on X about bridges, civil engineering, and infrastructure. The demolition and removal of the Carola Bridge is underway and will be completed soon. Will provide updates. (9/9)
Tweet media one
12
7
132